Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

KUB Fiber On Track To Reach 55,000 Fiber Customers By Year’s End

Knoxville Utilities Board remains on track to construct one of the biggest municipal broadband deployments ever attempted, and hopes to have delivered affordable fiber access to 55,000 Knoxville households and businesses before the end of the year.

In 2021, the Tennessee Valley Authority (TVA) and the state Comptroller’s office signed off on the utility’s long percolating plan to build a $702 million million fiber network.

Once completed, the network will provide affordable fiber access to 214,000 households across KUB’s 688-square-mile service area spanning Knox, Grainger, Union, and Sevier counties.

20,000 KUB customers in Inskip, Morningside, Park City and other parts of East Tennessee have already received access to the network, which provides residential customers with symmetrical gigabit fiber for $65 a month, symmetrical 2.5 gigabit service for $150 a month, and symmetrical 10 Gbps for $300 a month.

Business customers currently receive the option of a symmetrical 500 megabits tier for $85 a month, a symmetrical gigabit tier for $150 a month, or a Custom Connect Pro plan tailored to specific business bandwidth and reliability needs.

Despite Covid-related supply chain challenges, officials say the project remains on time and within budget. An estimated 35,500 more households should receive access over the next few months, with 55,000 total customers connected before the end of the year. The utility is promising to track project progress via an online deployment map.

KUB Fiber On Track To Reach 55,000 Fiber Customers By Year’s End

Knoxville Utilities Board remains on track to construct one of the biggest municipal broadband deployments ever attempted, and hopes to have delivered affordable fiber access to 55,000 Knoxville households and businesses before the end of the year.

In 2021, the Tennessee Valley Authority (TVA) and the state Comptroller’s office signed off on the utility’s long percolating plan to build a $702 million million fiber network.

Once completed, the network will provide affordable fiber access to 214,000 households across KUB’s 688-square-mile service area spanning Knox, Grainger, Union, and Sevier counties.

20,000 KUB customers in Inskip, Morningside, Park City and other parts of East Tennessee have already received access to the network, which provides residential customers with symmetrical gigabit fiber for $65 a month, symmetrical 2.5 gigabit service for $150 a month, and symmetrical 10 Gbps for $300 a month.

Business customers currently receive the option of a symmetrical 500 megabits tier for $85 a month, a symmetrical gigabit tier for $150 a month, or a Custom Connect Pro plan tailored to specific business bandwidth and reliability needs.

Despite Covid-related supply chain challenges, officials say the project remains on time and within budget. An estimated 35,500 more households should receive access over the next few months, with 55,000 total customers connected before the end of the year. The utility is promising to track project progress via an online deployment map.

KUB Fiber On Track To Reach 55,000 Fiber Customers By Year’s End

Knoxville Utilities Board remains on track to construct one of the biggest municipal broadband deployments ever attempted, and hopes to have delivered affordable fiber access to 55,000 Knoxville households and businesses before the end of the year.

In 2021, the Tennessee Valley Authority (TVA) and the state Comptroller’s office signed off on the utility’s long percolating plan to build a $702 million million fiber network.

Once completed, the network will provide affordable fiber access to 214,000 households across KUB’s 688-square-mile service area spanning Knox, Grainger, Union, and Sevier counties.

20,000 KUB customers in Inskip, Morningside, Park City and other parts of East Tennessee have already received access to the network, which provides residential customers with symmetrical gigabit fiber for $65 a month, symmetrical 2.5 gigabit service for $150 a month, and symmetrical 10 Gbps for $300 a month.

Business customers currently receive the option of a symmetrical 500 megabits tier for $85 a month, a symmetrical gigabit tier for $150 a month, or a Custom Connect Pro plan tailored to specific business bandwidth and reliability needs.

Despite Covid-related supply chain challenges, officials say the project remains on time and within budget. An estimated 35,500 more households should receive access over the next few months, with 55,000 total customers connected before the end of the year. The utility is promising to track project progress via an online deployment map.