Broadband Opportunity Program

Content tagged with "Broadband Opportunity Program"

Related Topics
Displaying 11 - 20 of 28

Conexon Connect Completes First Major Florida Fiber Deployment

Conexon Connect has completed its first fiber to the home project in Florida, a 2,000-mile network launched in partnership with Escambia River Electric Cooperative (EREC).

In a public statement, Conexon noted that this was the sixth fiber project they’ve completed nationwide with fiber Internet access being delivered to 12,000 EREC members.

Image
Escambia River Elec Coop Sign Cleaning with hose

"Over the past two years, we've worked tirelessly to bring this critical infrastructure to every EREC member in Escambia and Santa Rosa counties," EREC CEO Ryan Campbell said of the milestone. "Today, every member of our cooperative has access to fast, reliable Internet, which is not just about improving connectivity – it's about enhancing quality of life, fostering economic growth and ensuring that no one in our community is left behind in the digital age.”

Conexon’s Alexis Madison told ILSR that the EREC project will be financed with approximately $21.8 million in grants, including an Escambia County grant of $6.3 million, two Broadband Opportunity Program (BOP) grants totaling $5.9 million, and a Broadband Infrastructure Program (BIP) grant of $9.6 million.

Conexon Connect Completes First Major Florida Fiber Deployment

Conexon Connect has completed its first fiber to the home project in Florida, a 2,000-mile network launched in partnership with Escambia River Electric Cooperative (EREC).

In a public statement, Conexon noted that this was the sixth fiber project they’ve completed nationwide with fiber Internet access being delivered to 12,000 EREC members.

Image
Escambia River Elec Coop Sign Cleaning with hose

"Over the past two years, we've worked tirelessly to bring this critical infrastructure to every EREC member in Escambia and Santa Rosa counties," EREC CEO Ryan Campbell said of the milestone. "Today, every member of our cooperative has access to fast, reliable Internet, which is not just about improving connectivity – it's about enhancing quality of life, fostering economic growth and ensuring that no one in our community is left behind in the digital age.”

Conexon’s Alexis Madison told ILSR that the EREC project will be financed with approximately $21.8 million in grants, including an Escambia County grant of $6.3 million, two Broadband Opportunity Program (BOP) grants totaling $5.9 million, and a Broadband Infrastructure Program (BIP) grant of $9.6 million.

Conexon Connect Completes First Major Florida Fiber Deployment

Conexon Connect has completed its first fiber to the home project in Florida, a 2,000-mile network launched in partnership with Escambia River Electric Cooperative (EREC).

In a public statement, Conexon noted that this was the sixth fiber project they’ve completed nationwide with fiber Internet access being delivered to 12,000 EREC members.

Image
Escambia River Elec Coop Sign Cleaning with hose

"Over the past two years, we've worked tirelessly to bring this critical infrastructure to every EREC member in Escambia and Santa Rosa counties," EREC CEO Ryan Campbell said of the milestone. "Today, every member of our cooperative has access to fast, reliable Internet, which is not just about improving connectivity – it's about enhancing quality of life, fostering economic growth and ensuring that no one in our community is left behind in the digital age.”

Conexon’s Alexis Madison told ILSR that the EREC project will be financed with approximately $21.8 million in grants, including an Escambia County grant of $6.3 million, two Broadband Opportunity Program (BOP) grants totaling $5.9 million, and a Broadband Infrastructure Program (BIP) grant of $9.6 million.

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”

Suwannee Valley Electric Cooperative Should Light Up First Fiber Users By August

Suwannee Valley Electric Cooperative (SVEC) has begun construction on an ambitious new fiber deployment that will soon bring affordable, multi-gigabit fiber access to all of the cooperative’s existing electrical customers in rural Northern Florida.

Cooperative officials tell ILSR its three-phase build out is well underway, with a beta anticipated this summer and the first commercial customers connected by August. SVEC Communications Director Jon Little says the cooperative’s goal remains to deliver affordable fiber to all 20,000 of the cooperative's current electric customers by the end of 2026.

“We’ve broken our territory into three phases based partly on population or possible customers,” Little said.

The cooperative’s recently created subsidiary, Rapid Fiber Internet, will interface directly with subscribers, while Conexon manages deployment of more than 4,100 miles of fiber. Electrical users won’t see price hikes; the projected $93 million deployment cost will be funded by a combination of grants and loans paid back exclusively through user subscriptions.

Image
Suwannee Valley Electric Cooperative Rapid Fire Internet logo

Little told ISLR that make ready (preparing utility poles for fiber attachments) prep and engineering for phase one are complete, and make ready construction for phase one is roughly 40 percent complete. He added that primary fiber construction for phase one is roughly twenty percent complete.

“We’re hoping that we will have a group of beta customers starting next month,” Little said. “We want to go about a month to get their feedback, and so we’re still hoping sometime in August to offer hookups to our members on that first feeder.”