Court Sides With Louisville: One Touch Make Ready Is A-Ok

Louisville has overcome a tall hurdle in its efforts to bring better connectivity and more competition to the community through local control. On August 16th the U.S. District Court for the Western District of Kentucky supported the city’s one touch make ready (OTMR) ordinance. AT&T challenged the ordinance in court, but their arguments fell flat and court confirmed that the city has the authority to manage its rights-of-way with OTMR.

State Law

AT&T’s claim based on state law asserted that the city was overstepping its authority by enacting the OTMR ordinance because it was impinging on Kentucky Public Service Commission jurisdiction. AT&T attorneys argued that, according to state law, the PSC has exclusive jurisdiction over utility rates and services, but the court found that argument incorrect.

Within the state law, the court found that the OTMR ordinance fell under a carve-out that allows Louisville to retain jurisdiction over its public rights-of-way as a matter of public safety. The ordinance helps limit traffic disruptions by reducing the number of instances trucks and crews need to tend to pole attachments. The court wrote in its Order:

AT&T narrowly characterizes Ordinance No. 21 as one that regulates pole attachments. But the ordinance actually prescribes the “method or manner of encumbering or placing burdens on” public rights-of-way. … It is undisputed that make-ready work can require blocking traffic and sidewalks multiple times to permit multiple crews to perform the same work on the same utility pole…. The one-touch make-ready ordinance requires that all necessary make-ready work be performed by a single crew, lessening the impact of make-ready work on public rights-of-way. … Louisville Metro has an important interest in managing its public rights-of-way to maximize efficiency and enhance public safety. … And Kentucky law preserves the right of cities to regulate public rights-of-way. … Because Ordinance No. 21 regulates public rights-of-way, it is within Louisville Metro’s constitutional authority to enact the ordinance, and [the state law granting authority to the PSC] cannot limit that authority. 

Federal Jurisdiction

Indiana Eases Easements For Electric Co-ops; FIBRE Act

The State Legislature in Indiana sent SB 478 to Governor Eric Holcomb earlier this session; he recently signed the bill into law. Also known as the Facilitating Internet Broadband Rural Expansion (FIBRE) Act, the new law allows electric cooperatives with easements for electric lines to use those same easement for fiber infrastructure. The change in existing law will allow rural electric cooperatives to bring high-quality Internet access to the many rural regions in Indiana that are now unserved or underserved.

Updating Easements For Connectivity

SB 478 applies only to existing easements between electric suppliers and property owners. It doesn’t apply to new electric easements, railroad property, or the installation of new poles, conduit, or other structures. Other exceptions also apply to limit the new easement applications to existing infrastructure. 

The language of the bill provides in detail the steps that a property owner can take if they oppose the installation of the new infrastructure under the purview of an existing easement. It also lays out the information that an electricity provider must provide to the property owner regarding the plan for fiber infrastructure deployment and planned delivery. The bill goes on to establish further procedures if a property owner decides to pursue legal action if they feel their property value is decreased due to the new infrastructure or other related matters.

Lastly, the bill lays out procedural requirements for an electric cooperative that decides to offer broadband Internet. They must create a separate entity and maintain a separate accounting system.

Read the entire bill here.

Learning From The Co-op Guys

Republican State Senator Eric Koch, lead author on the bill, introduced the legislation as part of his ongoing efforts to improve connectivity in Indiana’s rural areas. According to a March article in the Indiana Economic Digest:

Famous Actors And Fast Access: FTTP Coming To Beverly Hills

Beverly Hills may be known for mansions and upscale shopping, but within a few years, it will also be known for fast, affordable, reliable connectivity. The city is investing in a citywide Fiber-to-the-Premise (FTTP) network for all homes and businesses, including apartments and condos, inside the city.

"90210" Wants Something Better

The city (pop. 35,000) is a little less than six square miles and they receive electricity from Southern California Edison (SCE). AT&T and Spectrum (formerly Time Warner Cable) provide Internet access throughout the community but a 2014 survey as part of the city’s feasibility study indicated that 65 percent of respondents would “definitely or probably” switch to services from the city, if the services were offered. As part of the survey, 25 percent of respondents also want video and voice bundles; 86 percent feel using the Internet at home is important.

While incumbents offer fiber connectivity in commercial areas of Beverly Hills, local businesses report that rates are expensive and they must pay for the cost of construction, which is also a big expense. At a recent City Council meeting when the Council approved funding for the project, the Mayor and Members expressed the need to be an economically competitive city. With Santa Monica, Culver City and Burbank nearby (all communities with municipal networks), Beverly Hills wants to be able to attract businesses looking to relocate or hold on to the businesses that need affordable and reliable gigabit connections.

Nuts And Bolts To Networking

seal-bev-hills-ca_0.jpeg

Locating Fiber: Local Leaders Can Help State Decision Makers

Better conduit policy and One Touch Make Ready (OTMR) are two approaches seeing the state legislative limelight recently. With local examples to offer guidance, a few state lawmakers are attempting to implement similar rules.

State Governments Follow Local Leads

Local communities know their needs best and are best poised to make local decisions. Some have used new conduit policies like in Mount Vernon, Washington. The community's ordinances require developers to install additional conduit during construction and then deed the conduit to the city. The additional expense is minimal and the additional asset makes the property Fiber-to-the-Premise (FTTP) capable, driving up its value. Developers don't consider the ordinance a burden.

Other communities have passed ordinances for OTMR. When Louisville, Kentucky, adopted OTMR to speed up deployment for new entrants, AT&T sued to stop the city, claiming that the FCC had jurisdiction over such decisions. In October 2016, however, the agency let the parties know that Louisville had opted out of federal pole attachment rules at an earlier date. Nashville, Tennessee, passed OTMR also and has also had to deal with incumbent lawsuits.

The overall goal is to make new networks less time-consuming and resource intensive to deploy. It also keeps communities free of constant construction noise and reduces traffic disruption, thereby improving the quality of life during the deployment. When an approach works on the local level, state lawmakers often want to reproduce it on a broader scale.

Transcript: Community Broadband Bits Episode 247

This is the transcript for Community Broadband Bits Episode 247. Ken Demlow of Newcom Technologies chats with Christopher Mitchell about what happened in Nashville and why poles are important for fiber. Listen to this episode here.

Ken Demlow: There's all that kind of communication that not only can improve what happens in electric and what happens in water, but also just such better communication with your customer, and it's all good stuff.

Lisa Gonzalez: This is episode 247 of the Community Broadband Bits Podcast from the Institute for Local Self-Reliance. I'm Lisa Gonzalez. Ken Demlow, Sales Director of Newcom Technologies joins Christopher this week to talk about several topics. In addition to discussing engineering and design and how it relates to telecommunications networks, Ken shares how Newcom is taking advantage of new technology to offer communities the best results. Christopher and Ken also get into the details of smart-grid and some benefits and uses that you might not necessarily think of right away. The guys spend some time on what happened in Nashville when Ken worked on the Google Fiber project. He shares his inside perspective. You can learn more about Newcom at nucomtech.com. Now, here's Christopher with Ken Demlow from Newcom Technologies talking about engineering and design, smart-grids, and pole drama in Nashville.

Christopher Mitchell: Welcome to another edition of The Community Broadband Bits Podcast. I'm Chris Mitchell. Today, I'm speaking with Ken Demlow, the sales director of Newcom Technologies. Welcome to the show.

Ken Demlow: Thank you. Good to be here.

Christopher Mitchell: Ken you're one of my favorite people at these trade shows. We're here at the Iowa Association of Municipal Utilities, and as you know, I contrived an excuse to have you on because I think you're a fun person to talk to.

Ken Demlow: Thank you. That's better than I deserve, but thank you.

Christopher Mitchell: I think we're going to start with just a brief explanation of what Newcom Technologies does.

Using Fiber for Smart Grid and the Pole Problem in Nashville - Community Broadband Bits 247

While at the annual Iowa Association of Municipal Utilities Broadband Conference, I forced Ken Demlow to be our guest on Community Broadband Bits Podcast 247. Ken is the Sales Director for Newcom Technologies, where he has worked with many different fiber-optic deployments on the ground and is a fun guy to talk to more generally.

Our discussion focuses on two main topics - the benefits of using fiber-optic connections to smart-grid applications rather than relying on wireless and the challenges that Google faced in getting on the poles in Nashville to build its fiber-optic network (which seems to be stalled). 

Ken had a front-row seat to the work in Nashville to get Google Fiber on poles but our conversation focuses on what is publicly known. We aren't breaking any insider secrets, but this is a very good discussion about the tremendous challenges of dealing with attachments on over 100,000 poles when contemplating a citywide metro fiber build. For people who haven't done it, this will explain why encouraging private sector competition at the physical network level is very difficult. And we keep it interesting - from possibly the worst idea for a sci-fi antagonist ever and how make-ready could fit into Greek myths.

This show is 29 minutes long and can be played on this page or via Apple Podcasts or the tool of your choice using this feed

Transcript below. 

We want your feedback and suggestions for the show-please e-mail us or leave a comment below.

Listen to other episodes here or view all episodes in our index. See other podcasts from the Institute for Local Self-Reliance here.

Thanks to Break the Bans for the music. The song is Escape and is licensed under a Creative Commons Attribution (3.0) license.

AT&T Tries to End the Magic of One Touch Make-Ready

On the border of Kentucky and Indiana a fight is brewing as AT&T and Google Fiber have both announced plans to bring Gigabit Internet service to Louisville, Kentucky. Home to over half a million, the city could see major economic development with new ultra high-speed Internet access, but there’s a problem: the utility poles.

AT&T is suing the city over a “one touch make-ready” ordinance. On February 11, 2016, the Louisville Metro Council passed the ordinance in order to facilitate new competitors, i.e. Google Fiber. 

Utility Poles: Key to Aerial Deployment

Make-ready is the shorthand for making a utility pole ready for new attachments. Although it may seem simple, this process is often expensive and time-consuming. To add a new cable, others may have to be shifted in order to meet safety and industry standards. Under the common procedure, this process can take months as each party has to send out an independent crew to move each section of cabling. 

To those of us unfamiliar with the standards of pole attachment it may seem absurd, but this originally made sense. Utility poles have a limited amount of space, and strict codes regulate the placement of each type of cable on the pole. Competitors feel they have to fiercely guard their space on the pole and cannot trust other providers to respect their cables. Make-ready must involve coordination between multiple providers and the utility pole owners. For some firms, like AT&T, this is an opportunity to delay new competition for months.

One Touch Make Ready and Wireless Innovation in Louisville - Community Broadband Bits Podcast 193

When we asked Ted Smith, Chief Innovation Officer of Louisville, Kentucky, to join us for episode 193 of the Community Broadband Bits Bits podcast, we expected to talk about the one touch make ready policy they had enacted (and AT&T has since sued to stop). We did, but we ended with a focus on how networking is already improving the city. 

We start off by focusing on the problem of adding new fiber networks to existing poles (many of which are owned by telephone company incumbents that are not particularly inclined to make life easy for new competitors). One touch make ready simplifies the process, resulting in many benefits for communities in addition to lowering the cost to build new networks. We explore that topic to start. But at the end of the discussion, Ted and I discuss what Susan Crawford has termed a responsive city approach - Louisville is using all kinds of network attached devices to improve city services in some of the lowest income neighborhoods. 

This show is 26 minutes long and can be played on this page or via Apple Podcasts or the tool of your choice using this feed

Transcript below. 

We want your feedback and suggestions for the show-please e-mail us or leave a comment below.

Listen to other episodes here or view all episodes in our index. See other podcasts from the Institute for Local Self-Reliance here.

Thanks to Kathleen Martin for the music, licensed using Creative Commons. The song is "Player vs. Player."

Explaining Right-of-Way Basics - Community Broadband Bits Episode 169

For this week's Community Broadband Bits, we are delving into an area of law and practice that is quite important for Internet network deployment but tends to be dry and confusing. Not for us today though, we have Sean Stokes, a Principal at Baller Herbst Stokes & Lide, joining us to explain Right-of-Way basics. We talk about what the public Right-of-Way (ROW) is, who is responsible for maintaining it, how entities can get access to it and how poles are distinct from the ROW. We discuss how much power local governments and pole owners have to deny access to these assets and some of the costs associated with make-ready. 

If you don't know what make-ready is, you'll know in less than thirty minutes. We finish our discussion by exploring the "Municipal Gain" policy in Connecticut, where munis are entitled to some space on the poles for any purpose they choose to use it. Historically, this was used only for public safety, but it was recently broadened. Sean also explores how he believes we should simplify access for fiber-optics rather than basing access on the particular end service being offered. 

This show is 30 minutes long and can be played on this page or via Apple Podcasts or the tool of your choice using this feed.

Transcript below.

We want your feedback and suggestions for the show-please e-mail us or leave a comment below.

Listen to other episodes here or view all episodes in our index. See other podcasts from the Institute for Local Self-Reliance here.

Thanks to bkfm-b-side for the music, licensed using Creative Commons. The song is "Raise Your Hands."

Princeton Voters Authorize FTTH Make-Ready Funds in Record Turn-Out

On November 18th, 90% of voters at Princeton's special town meeting approved a measure to fund $1.2 million in make-ready costs bringing the community one step closer to fiber connectivity. The number voters who attended the meeting broke the previous attendance record set 15 years ago by 30%.

We introduced the central Massachusetts town of 3,300 in 2013. The community suffered from poor Internet connectivity negatively impacting its schools, real estate market, and economic development. Since then, the community voted to create a Municipal Light Plant and to appropriate funds to keep the project moving forward.

Community leaders have investigated several options and last fall entered into a relationship with the Matrix Design Group. According to the Memorandum of Understanding [PDF], Matrix will design, build, and operate the FTTH network for a period of 20 years. At the end of that time period, Princeton Broadband Municipal Light Plant has the option of renewing that relationship or purchasing the network for $1.

As their contribution, Princeton will provide rights-of-way, police details during construction, powered telecom shelters, and will pay for utility pole make-ready costs. According to an article in the Landmark:

The make ready work includes replacing approximately 80 utility poles, and moving telephone and electrical lines on 450 poles, providing housing for the electrical components needed to operate the system, and paying for police details during the make ready work.

The borrowing is expected to cost the owner of a home valued at $300,000, about $10 a month or $115 a year increase on their taxes for 12 years. Internet service plus telephone will cost $115 a month. Once a contract is negotiated with Matrix, construction on the make ready phase would start in January 2015 and the project would be completed by January 2016.