Final Phase of Gigabit FTTH Deployment Begins in Erwin

What started as a pilot project back in 2014 has consistently expanded to more addresses. Now the “Little Gig City” has put a date on when they expect to complete the final phase of their community-wide fiber network — early 2020. “Right now we feel like we’re kind of in the home stretch,” says Erwin Utilities fiber optic engineer John Williams. 

When The Time Was Right

The small town of Erwin, Tennessee first explored the possibility of bringing Fiber-to-the-Home (FTTH) to its residents in 1999. At the time, however, the community chose not to pursue a publicly owned network because only 20 percent of homes in the area had a computer and the initial estimated cost of over $20 million was too high for local palates. The market changed over the next few years and in 2012, the town finally felt it was time to invest. They constructed a fiber backbone that connected 45 SCADA locations and six county schools. By 2014, the city announced plans to develop a pilot project for business and residential connectivity in the downtown area.

The pilot project reached approximately 1,000 premises; the utility’s goal was to achieve a 25 percent take rate to ensure the service would be self-sustaining. According to Williams, the utility swiftly surpassed their goal and are now at 36 percent subscribership in the original deployment area. Erwin Utilities has expanded, passing a total of approximately 5,000 premises out of 9,000 total potential premises, which are also electric service customers.

logo-erwin-fiber.jpg Because Tennessee municipal utilities are subject to state law that limits their Internet service area to their electric service footprint, Erwin can only provide connectivity to a limited number of premises. The law creates a situation that protects incumbent monopolies, but forces rural folks who obtain electric service from a different provider to rely on ISPs that generally offer poor Internet access options via DSL or expensive satellite service.

The Ultimate in Self-Reliance

Final Phase of Gigabit FTTH Deployment Begins in Erwin

What started as a pilot project back in 2014 has consistently expanded to more addresses. Now the “Little Gig City” has put a date on when they expect to complete the final phase of their community-wide fiber network — early 2020. “Right now we feel like we’re kind of in the home stretch,” says Erwin Utilities fiber optic engineer John Williams. 

When The Time Was Right

The small town of Erwin, Tennessee first explored the possibility of bringing Fiber-to-the-Home (FTTH) to its residents in 1999. At the time, however, the community chose not to pursue a publicly owned network because only 20 percent of homes in the area had a computer and the initial estimated cost of over $20 million was too high for local palates. The market changed over the next few years and in 2012, the town finally felt it was time to invest. They constructed a fiber backbone that connected 45 SCADA locations and six county schools. By 2014, the city announced plans to develop a pilot project for business and residential connectivity in the downtown area.

The pilot project reached approximately 1,000 premises; the utility’s goal was to achieve a 25 percent take rate to ensure the service would be self-sustaining. According to Williams, the utility swiftly surpassed their goal and are now at 36 percent subscribership in the original deployment area. Erwin Utilities has expanded, passing a total of approximately 5,000 premises out of 9,000 total potential premises, which are also electric service customers.

logo-erwin-fiber.jpg Because Tennessee municipal utilities are subject to state law that limits their Internet service area to their electric service footprint, Erwin can only provide connectivity to a limited number of premises. The law creates a situation that protects incumbent monopolies, but forces rural folks who obtain electric service from a different provider to rely on ISPs that generally offer poor Internet access options via DSL or expensive satellite service.

The Ultimate in Self-Reliance

Final Phase of Gigabit FTTH Deployment Begins in Erwin

What started as a pilot project back in 2014 has consistently expanded to more addresses. Now the “Little Gig City” has put a date on when they expect to complete the final phase of their community-wide fiber network — early 2020. “Right now we feel like we’re kind of in the home stretch,” says Erwin Utilities fiber optic engineer John Williams. 

When The Time Was Right

The small town of Erwin, Tennessee first explored the possibility of bringing Fiber-to-the-Home (FTTH) to its residents in 1999. At the time, however, the community chose not to pursue a publicly owned network because only 20 percent of homes in the area had a computer and the initial estimated cost of over $20 million was too high for local palates. The market changed over the next few years and in 2012, the town finally felt it was time to invest. They constructed a fiber backbone that connected 45 SCADA locations and six county schools. By 2014, the city announced plans to develop a pilot project for business and residential connectivity in the downtown area.

The pilot project reached approximately 1,000 premises; the utility’s goal was to achieve a 25 percent take rate to ensure the service would be self-sustaining. According to Williams, the utility swiftly surpassed their goal and are now at 36 percent subscribership in the original deployment area. Erwin Utilities has expanded, passing a total of approximately 5,000 premises out of 9,000 total potential premises, which are also electric service customers.

logo-erwin-fiber.jpg Because Tennessee municipal utilities are subject to state law that limits their Internet service area to their electric service footprint, Erwin can only provide connectivity to a limited number of premises. The law creates a situation that protects incumbent monopolies, but forces rural folks who obtain electric service from a different provider to rely on ISPs that generally offer poor Internet access options via DSL or expensive satellite service.

The Ultimate in Self-Reliance

Final Phase of Gigabit FTTH Deployment Begins in Erwin

What started as a pilot project back in 2014 has consistently expanded to more addresses. Now the “Little Gig City” has put a date on when they expect to complete the final phase of their community-wide fiber network — early 2020. “Right now we feel like we’re kind of in the home stretch,” says Erwin Utilities fiber optic engineer John Williams. 

When The Time Was Right

The small town of Erwin, Tennessee first explored the possibility of bringing Fiber-to-the-Home (FTTH) to its residents in 1999. At the time, however, the community chose not to pursue a publicly owned network because only 20 percent of homes in the area had a computer and the initial estimated cost of over $20 million was too high for local palates. The market changed over the next few years and in 2012, the town finally felt it was time to invest. They constructed a fiber backbone that connected 45 SCADA locations and six county schools. By 2014, the city announced plans to develop a pilot project for business and residential connectivity in the downtown area.

The pilot project reached approximately 1,000 premises; the utility’s goal was to achieve a 25 percent take rate to ensure the service would be self-sustaining. According to Williams, the utility swiftly surpassed their goal and are now at 36 percent subscribership in the original deployment area. Erwin Utilities has expanded, passing a total of approximately 5,000 premises out of 9,000 total potential premises, which are also electric service customers.

logo-erwin-fiber.jpg Because Tennessee municipal utilities are subject to state law that limits their Internet service area to their electric service footprint, Erwin can only provide connectivity to a limited number of premises. The law creates a situation that protects incumbent monopolies, but forces rural folks who obtain electric service from a different provider to rely on ISPs that generally offer poor Internet access options via DSL or expensive satellite service.

The Ultimate in Self-Reliance

Final Phase of Gigabit FTTH Deployment Begins in Erwin

What started as a pilot project back in 2014 has consistently expanded to more addresses. Now the “Little Gig City” has put a date on when they expect to complete the final phase of their community-wide fiber network — early 2020. “Right now we feel like we’re kind of in the home stretch,” says Erwin Utilities fiber optic engineer John Williams. 

When The Time Was Right

The small town of Erwin, Tennessee first explored the possibility of bringing Fiber-to-the-Home (FTTH) to its residents in 1999. At the time, however, the community chose not to pursue a publicly owned network because only 20 percent of homes in the area had a computer and the initial estimated cost of over $20 million was too high for local palates. The market changed over the next few years and in 2012, the town finally felt it was time to invest. They constructed a fiber backbone that connected 45 SCADA locations and six county schools. By 2014, the city announced plans to develop a pilot project for business and residential connectivity in the downtown area.

The pilot project reached approximately 1,000 premises; the utility’s goal was to achieve a 25 percent take rate to ensure the service would be self-sustaining. According to Williams, the utility swiftly surpassed their goal and are now at 36 percent subscribership in the original deployment area. Erwin Utilities has expanded, passing a total of approximately 5,000 premises out of 9,000 total potential premises, which are also electric service customers.

logo-erwin-fiber.jpg Because Tennessee municipal utilities are subject to state law that limits their Internet service area to their electric service footprint, Erwin can only provide connectivity to a limited number of premises. The law creates a situation that protects incumbent monopolies, but forces rural folks who obtain electric service from a different provider to rely on ISPs that generally offer poor Internet access options via DSL or expensive satellite service.

The Ultimate in Self-Reliance

Final Phase of Gigabit FTTH Deployment Begins in Erwin

What started as a pilot project back in 2014 has consistently expanded to more addresses. Now the “Little Gig City” has put a date on when they expect to complete the final phase of their community-wide fiber network — early 2020. “Right now we feel like we’re kind of in the home stretch,” says Erwin Utilities fiber optic engineer John Williams. 

When The Time Was Right

The small town of Erwin, Tennessee first explored the possibility of bringing Fiber-to-the-Home (FTTH) to its residents in 1999. At the time, however, the community chose not to pursue a publicly owned network because only 20 percent of homes in the area had a computer and the initial estimated cost of over $20 million was too high for local palates. The market changed over the next few years and in 2012, the town finally felt it was time to invest. They constructed a fiber backbone that connected 45 SCADA locations and six county schools. By 2014, the city announced plans to develop a pilot project for business and residential connectivity in the downtown area.

The pilot project reached approximately 1,000 premises; the utility’s goal was to achieve a 25 percent take rate to ensure the service would be self-sustaining. According to Williams, the utility swiftly surpassed their goal and are now at 36 percent subscribership in the original deployment area. Erwin Utilities has expanded, passing a total of approximately 5,000 premises out of 9,000 total potential premises, which are also electric service customers.

logo-erwin-fiber.jpg Because Tennessee municipal utilities are subject to state law that limits their Internet service area to their electric service footprint, Erwin can only provide connectivity to a limited number of premises. The law creates a situation that protects incumbent monopolies, but forces rural folks who obtain electric service from a different provider to rely on ISPs that generally offer poor Internet access options via DSL or expensive satellite service.

The Ultimate in Self-Reliance

Final Phase of Gigabit FTTH Deployment Begins in Erwin

What started as a pilot project back in 2014 has consistently expanded to more addresses. Now the “Little Gig City” has put a date on when they expect to complete the final phase of their community-wide fiber network — early 2020. “Right now we feel like we’re kind of in the home stretch,” says Erwin Utilities fiber optic engineer John Williams. 

When The Time Was Right

The small town of Erwin, Tennessee first explored the possibility of bringing Fiber-to-the-Home (FTTH) to its residents in 1999. At the time, however, the community chose not to pursue a publicly owned network because only 20 percent of homes in the area had a computer and the initial estimated cost of over $20 million was too high for local palates. The market changed over the next few years and in 2012, the town finally felt it was time to invest. They constructed a fiber backbone that connected 45 SCADA locations and six county schools. By 2014, the city announced plans to develop a pilot project for business and residential connectivity in the downtown area.

The pilot project reached approximately 1,000 premises; the utility’s goal was to achieve a 25 percent take rate to ensure the service would be self-sustaining. According to Williams, the utility swiftly surpassed their goal and are now at 36 percent subscribership in the original deployment area. Erwin Utilities has expanded, passing a total of approximately 5,000 premises out of 9,000 total potential premises, which are also electric service customers.

logo-erwin-fiber.jpg Because Tennessee municipal utilities are subject to state law that limits their Internet service area to their electric service footprint, Erwin can only provide connectivity to a limited number of premises. The law creates a situation that protects incumbent monopolies, but forces rural folks who obtain electric service from a different provider to rely on ISPs that generally offer poor Internet access options via DSL or expensive satellite service.

The Ultimate in Self-Reliance

Video: Morristown FiberNET Brings Jobs, Boosts Quality of Life

FiberNET, the municipal fiber network serving Morristown, Tennessee, has been serving the community since 2006 with fast, affordable, reliable Fiber-to-the-Home service. FiberNET is one of those networks that quietly went about its business bringing top notch services for residents, businesses, and institutions without a lot of fanfare. If you don’t live or work in the area or follow developments in broadband policy and implementation, you may not be familiar with Morristown’s FiberNET.

Now is your chance to learn more.

The community has produced a short, high-quality film about the network and the many ways it enhances living in Morristown for residents, businesses, and local entities. Business leaders describe how the network has enhanced and advanced their operations. Jody Wigington, who we’ve hosted on the Community Broadband Bits podcast, describes how the schools and local institutions have access to a network to rival any connections available in urban areas.

What’s the best part, in his opinion?

“We’re not-for-profit and locally owned. So FiberNET was built for the people through the vision of community leaders. And remember, FiberNET provides local jobs for the community and our employees are are part of the fabric of life in the Lakeway Region.”

Check it out:

Video: Morristown FiberNET Brings Jobs, Boosts Quality of Life

FiberNET, the municipal fiber network serving Morristown, Tennessee, has been serving the community since 2006 with fast, affordable, reliable Fiber-to-the-Home service. FiberNET is one of those networks that quietly went about its business bringing top notch services for residents, businesses, and institutions without a lot of fanfare. If you don’t live or work in the area or follow developments in broadband policy and implementation, you may not be familiar with Morristown’s FiberNET.

Now is your chance to learn more.

The community has produced a short, high-quality film about the network and the many ways it enhances living in Morristown for residents, businesses, and local entities. Business leaders describe how the network has enhanced and advanced their operations. Jody Wigington, who we’ve hosted on the Community Broadband Bits podcast, describes how the schools and local institutions have access to a network to rival any connections available in urban areas.

What’s the best part, in his opinion?

“We’re not-for-profit and locally owned. So FiberNET was built for the people through the vision of community leaders. And remember, FiberNET provides local jobs for the community and our employees are are part of the fabric of life in the Lakeway Region.”

Check it out:

Video: Morristown FiberNET Brings Jobs, Boosts Quality of Life

FiberNET, the municipal fiber network serving Morristown, Tennessee, has been serving the community since 2006 with fast, affordable, reliable Fiber-to-the-Home service. FiberNET is one of those networks that quietly went about its business bringing top notch services for residents, businesses, and institutions without a lot of fanfare. If you don’t live or work in the area or follow developments in broadband policy and implementation, you may not be familiar with Morristown’s FiberNET.

Now is your chance to learn more.

The community has produced a short, high-quality film about the network and the many ways it enhances living in Morristown for residents, businesses, and local entities. Business leaders describe how the network has enhanced and advanced their operations. Jody Wigington, who we’ve hosted on the Community Broadband Bits podcast, describes how the schools and local institutions have access to a network to rival any connections available in urban areas.

What’s the best part, in his opinion?

“We’re not-for-profit and locally owned. So FiberNET was built for the people through the vision of community leaders. And remember, FiberNET provides local jobs for the community and our employees are are part of the fabric of life in the Lakeway Region.”

Check it out: